the company Subways of Buenos Aires SE (SBASE) three seasons Delaware subway of the Buenos aires city (CABA) will improve closed from March to May 2023approx.
under the Comprehensive Station Renovation Plan They will be carried out works in 20 stations of the Buenos Aires subway that have: waterproofing tasks, painting, replacement of flooring and lighting, blacksmith work, rearrangement of the electrical wiring, adaptation of signage, placement of Braille signage on handrails and porticos, and new furniture on the platform, such as benches, baskets and ischial supports.

The renewal It will start at a station on the line C and two of line D whose objective is to “improve the existing infrastructure and optimize the travel experience of users”. The first stage works will also cover two stations of the line A and E.
Subway: Qualities are the three stations that can change names
Which are the three subway stations that will close for works in March 2023?
The following stations They will remain closed for two months. within the framework of a works plan:
Line C
- general san martin: from March 1
D line
- bulnes: from the March 8
- School of Medicine: March, 15th
They will restore the old subway terminals of CABA: how it will affect users
The travel alternatives
The route of each the subway lines under renovation will continue as usualso passengers will be able to travel without problems to the previous or following stations.
- general san martin C line: Users of this subway station have the option of using other nearby C line stations: terminal withdrawal (at 700 meters) or lavalle (at 750 meters).
- bulnes (line D): those people who need to get to the vicinity of said station may choose to use line D in Omen (at 550 meters) or Scalabrini Ortiz (at 650 meters).
- Or also travel in collective of lines 12, 39, 64 and 152, which make their way through Santa Fe Avenue.
- School of Medicine (line D): users of this station can use nearby stations callao (at 400 meters) or Pueyrredon (at 950 meters).

Comprehensive Subway Station Renovation Plan: all works
The company Subterráneos de Buenos Aires SE (SBASE) will carry out works in 20 stations of the Buenos Aires subwayo According to SBASE, the first tranche of reforms also includes the following stations whose works will begin “soon”.
Line A
E line

The second stage of reforms includes seven stations, although without confirmed dates:
- Carlos Gardel (line B)
- Pasteur-Amia (line B)
- Uruguay (line B)
- Omen (line D)
- Cathedral (line D)
- italy square (line D)
- courts (line D)
SUBE card: how much is the new negative balance
Meanwhile, the third and final stage will include:
- lime (line A)
- pellegrini (line B)
- Pueyrredon (line B)
- north diagonal (line C)
- July 9th (line D)
- Scalabrini Ortiz (line D)
- palermo (line D)
MS